Sites info

- Building site Tour The Link Apr 1, 2023 - Jun 30, 2023
- Construction site Edenn May 1, 2023 - Jul 31, 2023
- Deployment of the new heating network and its two substations - ZAC des Groues Feb 1, 2022 - Aug 31, 2023
- Place de La Défense Mar 1, 2021 - Sep 30, 2023
- Construction of school group 1 - ZAC des Groues Jul 1, 2021 - Jan 1, 2024
- Construction of the Engie Campus - La Garenne-Colombes Jul 1, 2021 - Jan 1, 2024
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Mar 31, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Sep 30, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 6, 2026
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
Building site Tour The Link
Apr 1, 2023 - Jun 30, 2023
The elevation of the wings is progressing! The teams will complete the base levels (from the ground floor to R+4) by the end of the month and then continue with the so-called "current" levels (from R+5). The 12 escalators positioned in the base have been installed in their final locations.
The first elevator, facilitating the movement of teams and the transport of materials, is being installed.
The installation of the façade protections is continuing and will be completed by the end of May.
The cranes were raised for the first time in mid-March. The first telescoping will take place at the beginning of May. These operations will continue throughout the structural phase, depending on the progress of the levels. At the same time, the backfilling of the first basement area is continuing in order to reach the required level for the installation of technical networks. In the Arch Wing, this area has also been punctuated by the first acoustic and thermal insulation work.
A key stage of the project is still to come: the start of the "closed-cover" work, i.e. the installation of the first façades in the next few weeks!
Start of work on the living quarters
A new, additional living quarters will soon be operational in the logistics zone located parallel to the ring road, to the west of the Vignes footbridge. The foundation work has been completed, leaving room for the installation of the framework. Built on five levels, it will meet the site's needs in terms of team accommodation until the end of the operation.
The first "bungalows" will be installed in May for a partial opening in June.
Projection June 2023 - View from the Vignes footbridge looking in the direction of Puteaux
Projection June 2023 - View from the circular boulevard
Find all the news on the construction site with the application " The Link La Défense ", available on Apple or Androïd !