Construction of Lot 1 - West Village - ZAC des Groues

Dec 31, 2021 - Jan 31, 2025

Developers: BNP Paribas Immobilier and Marignan Architects: L'AUC / Martin Duplantier / Chartier Dalix / Studio Muoto / Ignacio Prego Builders: 1A - Entreprise AGZ / 1B - Entreprise BJF Location: rue François Hanriot and rue Edouard Colonne, Nanterre

Project perspective with lot 1A to the north and lot 1B to the south

From wood to ceramics, multiple materials and architectural styles make up the 8 buildings and 246 apartments of West Village. The program is divided into two separate construction sites: lot 1A to the north, with a total of 111 apartments spread over 4 buildings, and lot 1B, with 135 apartments also spread over 4 buildings.

Lot 1A

Work progress: To date: structural work in progress

  • Start of works: December 2021
  • Filling of old quarries (injections): beginning of January 2022 - end of March 2022 (3 months)
  • Infrastructure (parking levels) / foundations: March 2023 - August 2023 (6 months)
  • Structural work: June 2023 - July 2024 (13 months)
  • Secondary structures: April 2024 - February 2025 (11 months)
  • Delivery: 1st quarter 2025

For questions: rodney.fakhry@realestate.bnpparibas

Worksite photo

Lot 1B

Work progress: To date: structural work in progress

  • Start of work: December 2021
  • Injections: early January 2022 - end March 2022 (3 months)
  • Infrastructure (parking levels) / foundations: early July 2022 - end December 2022 (6 months)
  • Structural work: December 2022 - April 2024 (16 months)
  • Secondary structures: December 2023 to December 2024 (12 months)
  • Delivery: 1st quarter 2025

For questions: s.latouche@marignan.immo

Worksite photo