Sites info
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Jun 30, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Paris La Défense redevelops rue Jules Ferry and rue Fauvelles around the future Engie Campus Jul 1, 2023 - Oct 31, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Jan 31, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Construction of lot 2 - Les Hallizées May 1, 2023 - Sep 30, 2025
- Work on public spaces at Jardin des Rails, rue Edouard Colonne and Place des Groues Oct 1, 2023 - Dec 31, 2025
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 31, 2028
Construction of Lot 1 - West Village - ZAC des Groues
Dec 31, 2021 - Jan 31, 2025
Developers: BNP Paribas Immobilier and Marignan Architects: L'AUC / Martin Duplantier / Chartier Dalix / Studio Muoto / Ignacio Prego Builders: 1A - Entreprise AGZ / 1B - Entreprise BJF Location: rue François Hanriot and rue Edouard Colonne, Nanterre
Project perspective with lot 1A to the north and lot 1B to the south
From wood to ceramics, multiple materials and architectural styles make up the 8 buildings and 246 apartments of West Village. The program is divided into two separate construction sites: lot 1A to the north, with a total of 111 apartments spread over 4 buildings, and lot 1B, with 135 apartments also spread over 4 buildings.
Lot 1A
Work progress: To date: structural work in progress
- Start of works: December 2021
- Filling of old quarries (injections): beginning of January 2022 - end of March 2022 (3 months)
- Infrastructure (parking levels) / foundations: March 2023 - August 2023 (6 months)
- Structural work: June 2023 - July 2024 (13 months)
- Secondary structures: April 2024 - February 2025 (11 months)
- Delivery: 1st quarter 2025
For questions: rodney.fakhry@realestate.bnpparibas
Worksite photo
Lot 1B
Work progress: To date: structural work in progress
- Start of work: December 2021
- Injections: early January 2022 - end March 2022 (3 months)
- Infrastructure (parking levels) / foundations: early July 2022 - end December 2022 (6 months)
- Structural work: December 2022 - April 2024 (16 months)
- Secondary structures: December 2023 to December 2024 (12 months)
- Delivery: 1st quarter 2025
For questions: s.latouche@marignan.immo