Paris La Défense construction site news

Construction of Lot 1 - West Village - ZAC des Groues

Dec 31, 2021 - Sep 30, 2024

Developers: BNP Paribas Immobilier and Marignan
Builder: undefined shell company
Location (streets): rue François Hanriot and rue Edouard Colonne, Nanterre

Perspective of the project with lot 1A to the north and lot 1B to the south

From wood to ceramics, multiple materials and architectures make up the 8 buildings and 246 flats of West Village. This programme is divided into two distinct building sites, lot 1A to the north representing a total of 111 flats spread over 4 buildings and lot 1B representing 135 flats also spread over 4 buildings.

Lot 1A

Work progress : To date: Foundation stage, end of piling / start of earthworks

  • Start of works: December 2021
  • Injections: early January 2022 - end March 2022 (3 months)
  • Infrastructure (parking levels) / Foundation: beginning of March 2023 - August 2023 (6 months)
  • Structural works: May 2023 - May 2024 (12 months)
  • Secondary works: March 2023 - November 2024 (8 months)
  • Delivery: 4th quarter 2024

Crane erection: 2 cranes will be required to build the project. The first crane (G1) of the operation will be installed within the plot until August 2023. The second crane (G2) will be in place until October 2023.

Construction site living quarters: the living quarters will be located at the edge of the plot, at the level of the Jardin des Rails and will be spread over two levels.

Construction site hours: 7am to 6pm

Site entrance: 28 rue François Hanriot

For any questions: sinclair.alleron@bnpparibas.com

Lot 1B

Work progress : To date: completion of the basement floor -1.

  • Start of works: December 2021
  • Injections: beginning of January 2022 - end of March 2022 (3 months)
  • Infrastructure (parking levels) / foundations: beginning of July 2022 - end of December 2022 (6 months)
  • Structural work: September 2022 - December 2023 (16 months)
  • Secondary works: September 2023 - September 2024 (12 months)
    • Delivery: 4th quarter 2024

Crane erection: 2 cranes will be required to build the project. The first crane (G1) of the operation will be erected in July 2022 within the plot until August 2023. The second crane (G2) will be erected in September 2022 within the plot until December 2023.

Construction site living quarters : The living quarters will be located inside the construction site, the entrance will be located on the François HANRIOT street side. It will be spread over two/three levels to reach a surface of 300m².

Construction site hours: 7am to 6pm

Site entrance: 60 rue François Hanriot.

For any questions : s.latouche@marignan.immo