Sites info

- Redevelopment of public spaces in the Corolles-Reflets-Iris neighborhood Oct 1, 2021 - Feb 28, 2023
- Rose de Cherbourg construction site: work schedule 1st quarter 2023 Jan 9, 2023 - Apr 1, 2023
- Place de La Défense Mar 1, 2021 - May 31, 2023
- Deployment of the new heating network and its two substations - ZAC des Groues Feb 1, 2022 - Jun 30, 2023
- Construction of school group 1 - ZAC des Groues Jul 1, 2021 - Jul 31, 2023
- Construction of the Engie Campus - La Garenne-Colombes Jul 1, 2021 - Jan 1, 2024
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Mar 31, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Sep 30, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 6, 2026
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
Construction of Lot 1 - West Village - ZAC des Groues
Dec 31, 2021 - Sep 30, 2024
Developers: BNP Paribas Immobilier and Marignan
Builder: undefined shell company
Location (streets): rue François Hanriot and rue Edouard Colonne, Nanterre
Perspective of the project with lot 1A to the north and lot 1B to the south
From wood to ceramics, multiple materials and architectures make up the 8 buildings and 246 flats of West Village. This programme is divided into two distinct building sites, lot 1A to the north representing a total of 111 flats spread over 4 buildings and lot 1B representing 135 flats also spread over 4 buildings.
- Lot 1A
Work schedule :
- Start of works: 31/12/2021
- Injections: start 06/01/2022 - end 31/03/2022 (3 months)
- Infrastructure (parking levels) / Foundation: beginning of April 2022 - end of November 2022 (7 months)
- Structural works: 04 April 2022 - August 2023 (16 months)
- Secondary works: July 2023 to July 2024 (12 months)
- Delivery: 3rd quarter 2024
Crane erection: 2 cranes will be required to build the project. The first crane (G1) of the operation will be erected in July 2022 within the plot until August 2023. The second crane (G2) will be erected in October 2022 within the plot until October 2023.
Construction site living quarters: the living quarters will be located at the boundary of the plot, at the level of the Jardin des Rails and will be spread over two levels.
Construction site hours: 7am to 6pm
Site entrance: 28 rue François Hanriot
For any questions: raphael.delegge@realestate.bnpparibas
- Lot 1B
Work schedule :
- Start of works: 31/12/2021
- Injections: start 06/01/2022 - end 31/03/2022 (3 months)
- Infrastructure (parking levels) / foundations: beginning of April 2022 - end of November 2022 (7 months)
- Structural works: 04 April 2022 - August 2023 (16 months)
- Secondary works: July 2023 to July 2024 (12 months)
- Delivery: 3rd quarter 2024
Crane erection: 2 cranes will be required to build the project. The first crane (G1) of the operation will be erected in July 2022 within the plot until August 2023. The second crane (G2) will be erected in September 2022 within the plot until December 2023.
Construction site living quarters : The living quarters will be located inside the construction site, the entrance will be located on the François HANRIOT street side. It will be spread over two/three levels to reach a surface of 300m².
Construction site hours: 7am to 6pm
Site entrance: 60 rue François Hanriot.
For any questions: s.simohammed@marignan.immo - number : 06 73 14 2 87