Sites info
- Modernization of covered lanes Mar 18, 2024 - Mar 20, 2024
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Mar 31, 2024
- Edenn site Oct 25, 2023 - Mar 31, 2024
- Preparatory work for line 15 Feb 19, 2024 - Mar 31, 2024
- Roadworks in Place Louise Bourgeois and on the RD913 Jan 8, 2024 - Apr 1, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Sep 30, 2024
- Paris La Défense redevelops rue Jules Ferry and rue Fauvelles around the future Engie Campus Jul 1, 2023 - Oct 31, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 31, 2028
Deployment of the new heating network and its two substations - ZAC des Groues
Feb 1, 2022 - Aug 31, 2023
The ZAC des Groues project involves extending the existing heating network supplying La Défense to serve the new buildings. The connection of the operation has also made it possible to initiate the greening of the entire network, whose energy mix will reach 50% renewable energy by the end of the year. Work on the deployment of this new network began at the beginning of 2022 with the construction of two substations in parallel. The aim is to be able to supply heating to the first building lots in the ZAC as soon as they are completed.
Location: one in the southern sector (Garenne) and one in the northern sector (Hanriot)
Start: February 2022
End: 3rd quarter 2023
Site contact: groues2030@parisladefense.com
Overall picture showing the location of the two substations