Sites info

- Rose de Cherbourg construction site: work schedule 1st quarter 2023 Jan 9, 2023 - Apr 1, 2023
- Place de La Défense Mar 1, 2021 - May 31, 2023
- Deployment of the new heating network and its two substations - ZAC des Groues Feb 1, 2022 - Jun 30, 2023
- Construction of school group 1 - ZAC des Groues Jul 1, 2021 - Jul 31, 2023
- Construction of the Engie Campus - La Garenne-Colombes Jul 1, 2021 - Jan 1, 2024
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Mar 31, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Sep 30, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 6, 2026
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
Tour Hekla
Sep 18, 2019 - Oct 31, 2019
Avancement des travaux
La grue G1 est maintenant installée, la G2 sera montée durant les weekends des 05, 12 et 19 octobre dans l’emprise du chantier. Les 131 pieux sont terminés ainsi que la phase de terrassement. Les 4 massifs sur lesquels reposeront les futurs poteaux intérieurs de la tour ont également été réalisés. Actuellement, les fosses des futurs monte-charges sont en cours de réalisation.
Coulage du radier
La prochaine étape importante est le radier. Il s’agit d’une dalle permettant de répartir les charges sur les pieux. D’une surface de 700 m² et 2,5 m d’épaisseur, le radier contient environ 343 tonnes de ferraillage et 1800 m3 de béton !