- Rose de Cherbourg construction site: work schedule 1st quarter 2023 Jan 9, 2023 - Apr 1, 2023
- Place de La Défense Mar 1, 2021 - May 31, 2023
- Deployment of the new heating network and its two substations - ZAC des Groues Feb 1, 2022 - Jun 30, 2023
- Construction of school group 1 - ZAC des Groues Jul 1, 2021 - Jul 31, 2023
- Construction of the Engie Campus - La Garenne-Colombes Jul 1, 2021 - Jan 1, 2024
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Mar 31, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Sep 30, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 6, 2026
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
Blaise Pascal Boulevard
Dec 10, 2021 - Jan 31, 2022
Full opening of the Boulevard