Construction of school group 1 - ZAC des Groues

Jul 1, 2021 - Jan 1, 2024

**The work undertaken by the City of Nanterre is continuing. The implementation of the façade is underway (installation of the cladding), as well as the interior work. Delivery of the school complex is scheduled for early 2024, with the opening to children at the start of the 2024 school year.

This facility will have 20 classrooms and an integrated leisure centre for kindergarten and elementary school children.

The 3-storey building, with a structure combining concrete and wood, will be composed of a vast hall, wide corridors and common areas.

A planted courtyard on the ground floor will provide large green spaces, interfacing with the Jardin des Rails, and the outdoor walkways extending the classrooms.

Another asset of the project is a roof equipped with a pergola made up of photovoltaic panels which will provide a shaded area for the students and produce energy for the building.

Provisional timetable for the works :

  • Start of works: June 2021
  • Injections, foundations: finished
  • Structural work: finished
  • Interior: in progress
  • Delivery: early 2024